Coding isn’t the bottleneck.

Set the weeks from your last project. Then make the coding faster, and see how far the finish date moves.

Your last project, in weeks

The starting weeks are an example. Set your own.

The finish date

As it was24 weeks

With faster coding21 weeks

The dashed line marks your finish date if coding took zero weeks.

Weeks saved3

Weeks, even with zero coding time18

Coding is 25% of this project. Make it 2x faster and you finish 13% sooner. Even if coding took no time at all, the project would still take 18 weeks.

Coding is 25% of this project. Make it 2x faster and you finish 13% sooner. Even if coding took no time at all, the project would still take 18 weeks.
Each stage, and what we do differently
StageWeeksWhat we do differently
Requirements4, unchangedA prototype before kickoff, changed live with your business in the room.
Approvals and access6, unchangedWe start building in our lab, set up to match your environment, while access is arranged.
Coding6 → 3Faster with AI, and an engineer reviews every change.
Testing3, unchangedTests are written with the code and run on every change, not saved for the end.
Release and readiness5, unchangedWork arrives as pull requests through your own pipeline and review.

Where does delivery time actually go?

Mostly to the stages around the code: requirements, approvals and access, testing, and release. In the example above, coding is a quarter of the project, so even instant coding leaves three quarters of the schedule as it was.

The time comes back when those stages change: a prototype before kickoff, work that starts before access arrives, tests that run on every change, and releases through your own pipeline.

More field notes, guides and tools

From our delivery work and from AI Enablement for Product & Engineering, our monthly advisory.